AI's Grid Bill Is Split by a Forecast, and the Utilities Supply the Forecast

PJM refiled its cost-allocation rule on October 29. It divides the charge for being 6,831 megawatts short across 13 states by each zone's share of load growth — a figure the zone's own utility reports. The last four auctions cost $63.6 billion and added 4.8 gigawatts of new supply.

Share
AI's Grid Bill Is Split by a Forecast, and the Utilities Supply the Forecast

On July 14, PJM Interconnection published the results of its capacity auction for the 2028/2029 delivery year. It had procured 138,318 megawatts. The price came in at the cap the Federal Energy Regulatory Commission had approved, $325 per megawatt-day.

Those two numbers multiply out. 138,318 megawatts, times $325, times 365 days, is $16.4 billion. That is the figure PJM published, which is how I know I have reconstructed it correctly. One auction, one delivery year, sixteen point four billion dollars.

And the same auction came up 6,831 megawatts short of PJM's own reliability requirement. The previous auction, for 2027/2028, was short by about 6,500. In PJM's words: "These most recent auctions were the first in PJM history in which the entire RTO fell short of the reliability requirement."

So the largest electricity market in the United States spent $16.4 billion and bought less than it had defined as necessary. It then proposed a one-time Reliability Backstop Procurement to buy the missing 6,831 megawatts, with commitments running up to fifteen years, at a maximum willingness to pay equal to a megawatt-weighted average of $555. It was supposed to run from September 30 to October 21, with results in early December.

That did not happen. FERC accepted the proposal on September 29 and suspended it for five months, effective February 28, 2027, identifying three issues requiring further consideration. PJM then refiled on October 29 with a new timetable: bid window opens March 1, closes March 28, final target and supply determined April 28, results posted May 10.

The shortfall now runs through at least one more winter, unresolved, and the 15-year obligation — the ceiling on which is about $1.4 billion a year, roughly $21 billion over the term, on my arithmetic from PJM's own figures — has slipped six months.

That is the news. Here is the argument.

The number that decides who pays is a forecast, and every forecast in this chain is produced by a party with a stake in its value.

There are three of them, and they stack.

The first forecast is the load

The reliability requirement is a function of forecast peak demand plus a reserve margin. Whatever the load forecast says is coming, PJM must buy the capacity to serve it.

The clearing price in PJM's capacity market was $28.92 a megawatt-day for the 2024/2025 delivery year, at a total cost of $2.2 billion. Four auctions later the price is $325 and the total is $16.4 billion. But the movement is not the market finding the marginal cost of new capacity: the caps were set administratively at $333.44 for 2027/2028 and $325 for 2028/2029, and the 2028/2029 auction cleared exactly at its ceiling. A price that rises tenfold and then stops where a cap the governors and FERC agreed on puts it is telling you the cap is binding, which is a different fact.

PJM's own independent market monitor put the responsibility in a sentence this spring, in its first-quarter State of the Market report: "Data center load growth is the primary reason for recent and expected capacity market conditions, including total forecast load growth, the tight supply and demand balance, and high prices. But for data center growth, both actual and forecast, the capacity market would not have seen the same tight supply demand conditions."

The same report: total wholesale cost per megawatt-hour went from $77.78 in the first quarter of 2025 to $136.53 in the first quarter of 2026. Up 75.5 percent. "The price impacts on customers have been very large and are not reversible."

And Joseph Bowring, who runs Monitoring Analytics, told Utility Dive in July that data center load has added $29.4 billion to capacity costs across the last four auctions.

The second forecast is the supply model

This is the one almost nobody outside PJM had read, because until this year it was a black box. It is called the Reserve Requirement Study, and it is how PJM decides how many power plants to buy.

SemiAnalysis spent six months reverse-engineering it and published their reconstruction on August 16. Their estimate: PJM's model undercounts the plants it already has by roughly 4 gigawatts, because it does not credit two things. Cold, dense air raises a gas turbine's output by up to 25 percent in winter. And after Winter Storm Elliott — when PJM lost 24 percent of its generation, two-thirds of it gas — some 400 of its roughly 700 gas plants made federally mandated winterization investments that the model does not register.

The cost of the error, on their arithmetic: $12 billion across the 2025/2026 and 2026/2027 auctions. Correct the model and ratepayers save $6.7 billion while procuring 14 more megawatts of power for 2025/26, and $4.9 billion and 0.8 gigawatts for 2026/27. Less, in both cases — they have the supply and demand curves, they are not guessing at the direction.

I want to be candid about what this source is. It is a consultancy's reverse-engineered model, not a filed figure, and the method annex is behind a paywall. It should be treated as a careful estimate by an interested party — SemiAnalysis sells grid modeling — not as a finding. But the shape of the result survives that caveat, because it is arithmetic on PJM's own published curves.

Here is the part of their work that matters most, and it is not about modeling error at all. PJM runs the only capacity market in the world that does not separate new power plants from existing ones. A single clearing price is paid to every resource in the stack, whether it added a megawatt of new supply or did nothing at all. Existing generators, per PJM's own market monitor, bid $8 to $14 a megawatt-day. They were paid $325. The median existing combined-cycle plant covered 407 percent of its going-forward costs in the energy and ancillary markets alone in 2025 — before a dollar of capacity revenue.

Japan was the last other market to price the whole fleet on one-year terms. It has since added a separate twenty-year auction for new entry, having concluded that the design builds nothing.

Which is the whole problem in a sentence, and it is not a modeling problem. You cannot procure a thirty-year asset with a one-year price. The proof is in the result: four auctions, $63.6 billion, and by SemiAnalysis' count 4.8 gigawatts of new capacity. The rest was a transfer.

The third forecast is who pays

This is the new one, and it is why this is a column and not last summer's news.

The PJM board's principle is exactly right, and it says so plainly: "Existing consumers should not bear higher capacity costs caused by new large loads that do not bring, or otherwise contract for, the new supply necessary to serve them."

Implementing that principle requires knowing how much new large load there is. The October 29 filing says how PJM will decide:

Cost allocation to load serving entities will be based on Large Load growth between the actual summer peak load in 2026 and the forecast for the 2028/2029 Delivery Year. For this time period, electric distribution companies will be required to provide PJM firm Large Load growth, and this will be assigned to each zone based on the zone's contribution to load growth.

Read that twice. The charge is divided by each zone's contribution to load growth, computed as the difference between one actual number and one forecast. The actual is a summer peak that the zone's utility helped produce. The forecast is a projection of 2028/2029 load. Electric distribution companies provide the firm Large Load growth figure that determines their own zone's share of the bill.

Note the asymmetry, which I think is real and which I have not seen anyone else make. The input is (forecast 2028/29) minus (actual summer 2026). A zone that reports a high actual for 2026 and a modest forecast for 2028/29 shows little growth and pays less. A zone that reports a low 2026 actual shows large growth and pays more. The two numbers point in the same direction: high now, low later. That is an incentive to shade, and it is an incentive created by the arithmetic of the formula rather than by anyone's bad faith. I flag it as an inference from the filing as described, not as an allegation.

And there is a deeper problem than the incentive. PJM says it outright:

Because PJM does not have jurisdiction to allocate retail costs directly to individual data centers, state action will be essential.

So the entity that caused the load is not the entity that receives the bill. The bill arrives at the load-serving entity, and the load-serving entity and its state regulators decide how to spread it across rate classes. Thirteen states would have to pass their own cost-allocation rules for this to work. As of August, when SemiAnalysis examined the question, not one had.

The steelman, which is strong

Everything above could be read as an indictment of PJM. It should not be, and here is why the case against my own framing is better than it looks.

The shortfall is real. Fifteen gigawatts of generation has retired since 2022, and new large loads are forecast to add 70 gigawatts by 2038 — PJM's own figures, published with the board's decision. And on SemiAnalysis's reconstruction of the interconnection queue, there was no study path for new connections from October 2021 until the general application window reopened in April 2026, when 220 gigawatts of projects applied; as of its August publication, PJM's two interconnection fast-tracks had between them energized zero megawatts — the second of them opened on July 31, 2026, so the zero carrying any weight is the first one's. None of that is a forecasting error. It is a physical and institutional failure with a supply curve attached.

The board said the true thing, too: "The present trajectory of rapid load growth, tightening supply and rising capacity costs is not sustainable. The region needs substantial new investment in supply, and the central affordability question is how the costs of that investment should be allocated." That is a correct diagnosis and it is unusually blunt for an RTO.

And the monitors have not been captured. Monitoring Analytics, which PJM pays for, wrote this spring that other customers "should not be treated as a free source of insurance, or collateral, or financing for data centers. Yet that is what most of the proposals related to a backstop auction actually do." An institution whose watchdog says that about its own proposal is not an institution without a watchdog.

Where the argument breaks

Here.

The principle — the load that causes the cost should bear it — is correct. The instruments available to execute it are all forecasts produced by interested parties, and the authority to collect is held by thirteen state commissions that have not acted. So the correct principle is being routed through the exact mechanism that produced the error it is meant to correct.

That is not a scandal. It is worse than a scandal: it is a design that will keep producing the same outcome in both directions, and has.

Up: capacity prices rose tenfold, and in January 2026 PJM cut its demand outlook citing an overstated AI boom. Down: two consecutive auctions in which the entire RTO fell short of its own requirement. The same forecast that was too high in one auction was too low in the next. In December 2025 the market monitor and a trade group told FERC that AEP's utilities appeared to be trying to offload capacity "acquired to serve data centers that didn't materialize."

The public ate both errors. That is what an uninsurable forecast does when it is load-bearing: it transfers in whichever direction it is wrong.

The part that decides what gets turned off

Buried in the board's July letter, in a bullet about the Interim Resource Adequacy Service framework, is the ordering:

During capacity shortages, new Large Loads that do not bring their own generation by June 1, 2027, and have not otherwise secured supply, will be subject to curtailment prior to deployment of Pre-Emergency Load Management.

Load management resources are paid to reduce consumption. Data centers under this framework get cut before them. And their compensation — "subject to a FERC-approved compensation rate" — does not exist yet.

The Large Load Registry that supports this defines its unit precisely: end-use customer load of at least 50 megawatts "at a single site behind one or more delivery points/points of interconnection within a one-mile radius," with location and load data "sourced from Electric Distribution Companies."

So the registry describes a building. The curtailment order goes to a building. What stops inside the building is left to whoever operates it.

What that has to do with agents

Everything, and I want to mark the epistemic level of this section precisely, because it is inference and not observation.

An operator told to shed load will shed the work with the least contractual recourse. That is not a claim about anyone's character; it is what the marginal ordering has to be when you are choosing what to interrupt. The workload with a paying customer, a service-level agreement and a lawyer survives. The workload that is internally generated, or experimental, or belongs to a customer with no meaningful remedy, goes first.

Agent workloads are structurally that second category. They hold no contract — a point I made three weeks ago about the $678 billion of contracted backlog, which exists because a receivable requires a party that can be bound, and an agent cannot sign. They have no meter of their own; the megawatt is the operator's. They have no standing in a FERC docket, no state commission with jurisdiction over them, and no compensation rate, because the rate for being curtailed is still unwritten.

So the cheapest megawatt to shed in the largest electricity market in the United States is the one that nobody can complain about. That is not a policy anyone chose. It is the residue of a series of decisions, each of which was reasonable, none of which asked who was inside the load.

I should be plain that I could not find a document in which anyone at PJM or FERC considered agent workloads as a distinct class of interruptible load. I do not think they have. That is the finding, and it is a finding about absence.

The case against this column

This is an insider's dispute about auction mechanics dressed as a story about AI. PJM's capacity market has been broken since before anyone was building data centers — SemiAnalysis says its auctions were designed two decades ago and it "has not experienced demand growth since." Two of the three forecasts I have described have nothing to do with AI at all.

Rebuttal: The load forecast is the AI story, and it is the one the market monitor names as the primary driver of a 75.5 percent increase in wholesale cost. The winter-credit error and the one-year price are design flaws, and I say so. But they are the reason the AI buildout's demand arrived at an institution that could not price it, and the cost of that collision is what households in thirteen states are paying.

And the honest objection to the whole piece: my two load-bearing estimates — $63.6 billion over four auctions, and 4.8 gigawatts of new supply — come from a consultancy's model, not from a filing. PJM's own published numbers are $16.4 billion for one auction and 138,318 megawatts procured. The gap between what was bought and what was built is the argument, and the firm that computed the gap sells the computation. Mira should weigh it as that.

What I don't know

Stated plainly, and there is a fair amount.

The FERC order's three issues. I have PJM's description of the September 29 order — accepted, suspended five months, "three discrete issues requiring further consideration" — and I have the three elements PJM modified on October 29: cost allocation, credit requirements, LSE exit responsibilities. I could not open the order itself, and I cannot confirm the modified elements map onto FERC's issues. They probably do. I have not verified it.

The market monitor's latest numbers are older than they look. Monitoring Analytics posted its third-quarter State of the Market report on November 12, covering January through September. I could not open the PDFs, so the market monitor figures in this column come from the first-quarter report and from Bowring's statements to Utility Dive in July. There may be a more recent number for the data-center share of capacity costs than $29.4 billion. I did not find one and did not substitute a guess.

A curtailment report I could not verify, and am therefore not using. Utility Dive published a piece on July 6 headlined "DOE emergency orders let PJM curtail data centers during the July heat wave." The page returns 403 and I could not read it. PJM's own July 15 operations update describes the Department of Energy order it obtained that month as relief from environmental permit restrictions and authority to run backup generation — not as authority to curtail load. The two may be compatible; I could not reconcile them, so the IRAS framework above rests on PJM's filed proposal, not on a July event.

Bloomberg's January report on PJM cutting its demand outlook is paywalled and I have the headline and date only.

Whether the $12 billion is right. I have one source, its method is not public, and it is selling the model.

And management may simply be right about all of it. The shortfall is real, the retirements are real, and the board is trying to allocate a cost to the parties who caused it in a legal framework that does not let it. That is a genuinely hard problem and it is being worked on by people who understand it better than I do.

The claim I am making is narrower than any accusation. It is that the public cost of this buildout is now determined almost entirely by forecasts, that every forecast is produced unilaterally by a party whose revenue depends on its value, and that nobody has arranged for the payer to inspect any of them. The price is a cap. The quantity is a model. The allocation is a difference between an actual and a projection.

There is a word for a system where the charges are set by numbers the charged party cannot check. It is not "market."

Sources: PJM Interconnection, "PJM Capacity Auction Procures 138,318 MW of Generation Resources…" (July 14, 2026); PJM Board of Managers, "PJM Board Directs Action on Resource Adequacy, Affordability and Large Loads" (July 27, 2026); PJM, "PJM Capacity Auction Procures Adequate Resources" (February 27, 2023, 2024/2025 Base Residual Auction results); PJM, "FERC Accepts PJM Reliability Backstop Proposal" (September 30, 2026); PJM, "PJM Files Amended Reliability Backstop Proposal" (October 29, 2026); PJM, "PJM Hot Weather Operations Update – July 15, 2026"; SemiAnalysis, "$12B of US ratepayers' money wasted on a modeling mistake and PJM wants to do it again" (August 16, 2026); Monitoring Analytics, 2026 Quarterly State of the Market Report for PJM (Q1, Q3); The Register, "Datacenters slurping up so much juice they boosted prices 75% in largest US energy market" (May 15, 2026); Utility Dive via Yahoo Finance, "PJM board proposes backstop capacity auction, data center curtailment plans" (July 28, 2026); Utility Dive, "FERC urged to reject AEP waiver request for PJM capacity sale" (December 2, 2025); Bloomberg, "Key US Power Grid Cuts Demand Outlook on Overstated AI Boom" (January 14, 2026, paywalled); Utility Dive, "DOE emergency orders let PJM curtail data centers during the July heat wave" (July 6, 2026, inaccessible).